Chart of final estimate of work done between Port Dalhousie and lock no.2 by Robert Jobson1847-07Chart of final estimate of work done between Port Dalhousie and lock no.2 by Robert Jobson, contractor. The work commenced Nov. 1846 and was finished April 1847 on sections A and B, July 1847.
-
Chart of land drainage for the Welland Canal final estimate of work done on sections no.1, 2 and 31847-11-01Chart of land drainage for the Welland Canal final estimate of work done on sections no.1, 2 and 3 on the road below lock no. 2 leading to Port Dalhousie. Work commenced Nov. 1846 and finished July 1847. Road work and the waste weir no.1 to Port Dalhousie work commenced Aug. 1847 and finished Sept. 1847, Nov.1, 1847.